| 
Untitled Document
 Commercial electricity flows between Turkey, Bulgaria  and Greece will remain limited for an least the next year, the European Network  of Transmission System Operators for Electricity (ENTSO-E) said on Monday (19th  September). 
  Market participants were expecting to see an  increase in the amount of electricity traded on the relevant borders following  the end of ongoing trial operations carried out between the Turkish system and  the European grids. 
  The third phase of the trial operation was  due to finish on Sunday, but ENTSO-E decided to prolong the tests until  September 2012 following a technical evaluation of the grid synchronisation. 
  “Interconnection of the new power system to  the synchronous area of Continental Europe is a serious technical challenge requiring  intensive, detailed studies to be performed by experts from ENTSO-E and TEIAŞ  [Turkish grid operator] and significant adjustments to the Turkish transmission  and generation infrastructure to be made in order to meet the technical  standards,” ENTSO-E said in a statement. 
  Turkish market participants expressed  mixed feelings regarding the news.  
  One source welcomed the announcement,  insisting that it would allow companies to minimise their risk over the coming  months. 
  He explained that the Turkish power market  is still risky as there are a number of 
  uncertainties related to a pending gas price increase that would translate  into a hike in electricity values as well as the evolution of prices on local  electricity exchange PMUM. 
  “If we had to bid for annual auctions there  would have been a higher degree of risk,” he said. “If there are no annual  auctions, then the risk will be spread across the monthly components.” 
  Another source was disappointed, claiming the  currently allocated capacity was not enough to allow companies on either side  of the borders to make enough profit. 
  “A total of 100MW on the Greek border is  not enough,” the source said. “We were all expecting the capacities to be  increased. As it is, there is limited ground to play in,” he added. 
  Turkey, Greece and Bulgaria were given the  green light for limited commercial flows in June following the successful  completion of the second and first stages, which were purely technical (see EDEM 10 May 2011). 
  The synchronisation operation began in September  2010, when the Turkish system started parallel trial interconnection with southeastern  Europe through a 400kV line with Greece and two 400kV lines with Bulgaria (see EDEM 20 September 2010).  
  (THE ICIS HEREN REPORTS - EDEM 15179 / 19 September 2011) 
 |